NEC4 Tools for Engineers, by an Engineer

Free tools for NEC4 Compensation Events, Working Days, and Clause Reference. Built by a practising NEC4 professional for the global engineering community.

Contract Profile
Hong Kong Edition ยท Option A
Calendar Days Calculator
Calculate calendar days between dates, or add days from a start date. Ref: NEC4 Clause X60.1

โš ๏ธ Result is for reference only. Actual CE periods should be determined per contract terms and professional advice.

Working Days Calculator
Business days between two dates, including or excluding weekends and public holidays. Ref: NEC4 Clause X60.1

โš ๏ธ Result is for reference only. Actual CE periods should be determined per contract terms and professional advice.

CE Cost Calculator
Build a CE quotation including direct costs, prolongation (EOT), overhead, and fee. Option A/B uses rates; Option C/D uses Defined Cost + Fee.
Contract Profile
Hong Kong Edition ยท Option A
0

โš ๏ธ For Option A/B: use rates from Activity Schedule/BoQ. For Option C/D: use Defined Cost + Fee. Prolongation applies when a CE extends the planned Completion Date.

Programme Delay Analyzer
Track and analyse programme delays against the planned programme. Identifies critical path impact, float consumption, and total project delay. Ref: NEC4 ECC clause 63.3
Activity NamePlanned StartPlanned EndActual StartActual EndStatusPlanned
Dur.
Actual
Dur.
Delay
โ€”โ€”โ€”

โš ๏ธ Result is for reference only. Actual delay analysis should be determined per contract terms and professional programming advice. Float consumption assumes non-critical activities consume float before impacting the critical path.

Early Warning Generator
NEC4 Clause 16.1 โ€” Fill in the details below and the system will draft a professional Early Warning notice in Word format.

Project Information

The Matter / Issue

๐Ÿ“ˆ Potential Impact

โœ… Actions & Mitigation

โš ๏ธ Ref: NEC4 Clause 16.1 โ€” The Contractor and Project Manager notify the other Party as soon as either becomes aware of any matter that could affect the Price, Completion Date, or Quality of the Works. This tool helps draft the notification; always review before submission.

CE Notification Draft (Clause 61.3)
Draft a professional Compensation Event notification letter under NEC4 Clause 61.3.
CE Quotation Draft
Draft a professional Compensation Event quotation with cost breakdown and fee calculation.