NEC4 Clause 63: How Compensation Events Are Assessed โ Prices, Defined Cost and Delay
TL;DR
---
NEC4 Clause 63: How Compensation Events Are Assessed
If you manage NEC4 ECC contracts, compensation events (CEs) are the engine of change management. Clause 63 is the rulebook for assessing them. Get the assessment wrong and you will either under-recover or over-claim โ both of which create friction on site.
This guide explains what Clause 63 actually says: the dividing date, how the change to the Prices is assessed, how delay is measured, and when the Prices may be reduced.
The Core Rule: Clause 63.1 and the Dividing Date
Clause 63.1 states that the change to the Prices is assessed as the effect of the compensation event upon:
The **dividing date** is critical. For a compensation event that arises from the Project Manager or the Supervisor giving an instruction or notification, issuing a certificate, or changing an earlier decision, the dividing date is the date of that communication. For other compensation events, the dividing date is the date of the notification of the compensation event.
Work done up to the dividing date is assessed on actual Defined Cost; work not yet done is assessed on a forecast. This is why the assessment is a forecast exercise for the remaining work โ not an audit of the Contractor's final accounts.
Defined Cost: What Counts?
Defined Cost means the cost of the components in the Schedule of Cost Components (or the Short Schedule of Cost Components for Options A and B) โ the cost of people, equipment, plant, materials, charges and subcontractors as stated in those schedules, less Disallowed Cost. Head office overheads and profit are not part of Defined Cost; they are covered by the Fee.
For Options C, D, E and F, the Contractor records actual Defined Cost in its accounts and the assessment uses those amounts. For Options A and B, the quotation for a compensation event is based on the rates and lump sums in the Activity Schedule or Bill of Quantities, or โ where those do not cover the work โ the People Rates stated in the Contract Data. Clause 63.2 also lets the Project Manager and the Contractor agree rates or lump sums to assess the change to the Prices, which is often the most practical route.
The Fee: Your Only Mark-Up
The Fee is the percentage stated in the Contract Data, applied to Defined Cost. It covers the Contractor's overheads, profit and risk. You do not add any other mark-up on top. If the Contractor uses a Subcontractor, the Subcontractor's Defined Cost is assessed first and the Contractor's Fee is applied to it โ but the Fee is not applied twice.
Assessing Delay: Clause 63.5
Delay is assessed separately. Clause 63.5 states that a delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme current at the dividing date. The same approach applies to a delay to a Key Date, measured against the planned date when the Condition stated for the Key Date will be met.
Clause 63.6 adds that the assessment takes into account any delay caused by the compensation event already in the Accepted Programme and events which have happened between the date of the Accepted Programme and the dividing date โ so delay already allowed for is not double-counted.
When the Prices Are Reduced: Clauses 63.3 and 63.4
If the effect of a compensation event is to reduce the total Defined Cost, the Prices are **not** reduced unless the contract states otherwise. The Prices are reduced only in two situations under Clause 63.4: where the event is a change to the Scope (other than Scope provided by the Client) which the Contractor proposed and the Project Manager accepted, or where the event is a correction to an assumption stated by the Project Manager when assessing an earlier compensation event.
Other Assessment Rules Worth Knowing
The Role of the Project Manager and Contractor
The Contractor submits a quotation when instructed (Clause 62 โ normally within three weeks, with the Project Manager replying within two weeks). If the Contractor does not submit a quotation in time, or the Project Manager decides the assessment is incorrect, the Project Manager may assess the event themselves under Clause 64. The Project Manager notifies the Contractor of its assessment and gives details (Clause 64.3).
Common Mistakes to Avoid
Worked Example (Option C)
**Situation:** Under an Option C (target cost) contract, a change to the Scope requires an extra 200m of ductile iron pipe in a trench.
**Assessment:**
**The same event under Option A** would be priced using the rates and lump sums in the Activity Schedule (or the Bill of Quantities under Option B), not by building up Defined Cost from scratch.
Key Takeaways
---
**Category:** Compensation Events
**Tag:** NEC4, Clause 63, Defined Cost, Fee, Delay, Dividing Date