Acceptance and Reply Periods
The period for reply or acceptance is the period stated in the Contract Data. If no period is stated, it is two weeks.
Track all reply periods diligently. Late responses can result in deemed acceptance of proposals.
Two weeks is the default. If the Contract Data specifies a different period, use that instead.