Section 2The Contractor's Main Responsibilities

Clause 21.1

Design Liability

Purpose

The Contractor's design liability is fitness for purpose unless the Works Information states otherwise.

Practical Application

This is a key risk allocation. Contractors should consider design review periods and insurance requirements.

Common Pitfalls

Professional indemnity policies often exclude fitness for purpose. Review insurance before accepting design responsibility.

Related Clauses