Removing Equipment
The Contractor removes Equipment from Site when no longer needed.
The PM may instruct removal of redundant Equipment to free up space. The Contractor complies at their own cost.
If the Contractor does not remove Equipment, the Employer may remove and sell it, deducting costs.