Termination Procedure
The terminating party notifies the other of the reason and certifies the grounds.
Termination by the Employer: the PM certifies the reason and the Contractor leaves Site.
Termination by the Contractor requires PM non-compliance with payment obligations.
⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.