Key Persons
The Contractor's key persons are identified in the Contract Data. The Contractor cannot replace a key person without the PM's acceptance of the replacement.
Key persons include the project manager, site manager, and design lead. Their roles are critical to project delivery.
Replacing a key person without acceptance may be a breach. The PM's refusal to accept a replacement must be on reasonable grounds related to suitability.