Access to the Site
The Employer provides access to the Site on the starting date. The Contractor has access for as long as needed.
Site access is an Employer obligation. Delayed access may be a CE under 60.1.
Access conditions (how much, when, with what restrictions) should be clearly defined in the Works Information.