Section 3Time

Clause 30.1

Starting and Completion

Purpose

The Contractor starts on or before the Starting Date and achieves Completion by the Completion Date.

Practical Application

The starting date and completion date are stated in the Contract Data. Both can be changed by CEs.

Common Pitfalls

Failure to start on time can affect the Accepted Programme and CE assessments.