Section 3Time

Clause 31.2

Programme Content

Purpose

The programme shows: order and timing of work, float, risk allowances, method statements, and key dates.

Practical Application

The Accepted Programme is the baseline for all CE delay assessments. Its quality directly affects CE outcomes.

Common Pitfalls

The programme should clearly show float ownership. NEC4 defaults float to the Contractor unless stated otherwise.

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.