Assessing CE — Cost
Cost assessment method depends on Main Option. Option A/B: rates from Activity Schedule/BoQ. Option C/D: Defined Cost plus Fee.
Contract Profile selection is critical. The assessment method changes completely between Options. Tools on this site adjust accordingly.
Under Option C/D, the Contractor must demonstrate actual Defined Cost with records. Under Option A/B, the rate in the schedule applies.