Section 3Time

Clause 30.2

Completion

Purpose

Completion is achieved when the Contractor has done all work stated in the Works Information to be done by Completion and corrected notified Defects.

Practical Application

Completion is not the same as 'practical completion' in JCT. It requires all work and defect correction.

Common Pitfalls

If defects remain uncorrected at Completion, the Employer may assess delay damages and have defects corrected later.

Related Clauses