Completion
Completion is achieved when the Contractor has done all work stated in the Works Information to be done by Completion and corrected notified Defects.
Completion is not the same as 'practical completion' in JCT. It requires all work and defect correction.
If defects remain uncorrected at Completion, the Employer may assess delay damages and have defects corrected later.
⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.