Programme Acceptance
The PM accepts the programme if it complies with the contract and shows realistic plans.
The PM may reject a programme if it is unrealistic or incomplete. Reasons for rejection must be given.
An unrealistic programme (e.g., compressed durations) can be rejected. PM rejection within reply period prevents deemed acceptance.
⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.