Clause 35.1

Completion Certificate

Purpose

The Supervisor certifies Completion within one week of Completion being achieved.

Practical Application

The Completion Certificate triggers key milestones: retention release, defect corrections period, and delay damages cessation.

Common Pitfalls

If the Supervisor does not certify promptly, Completion is treated as certified on the date it was achieved.

Related Clauses