Notification of Defects
The Supervisor notifies the Contractor of defects.
Defects are matters not in accordance with the Works Information. The Contractor corrects them.
Defect correction is at the Contractor's own cost unless the defect is due to an Employer risk or PM instruction.
⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.
NEC4 Assistant
Free Search
AI responses are for reference. Verify with a qualified professional.