Section 5Payment

Clause 52.2

Defined Cost — Disallowed Cost

Purpose

Disallowed Cost includes costs that are not justified by the Contractor's records or are not incurred in Providing the Works. The PM assesses the amount of Disallowed Cost.

Practical Application

Under options C, D, and E, the PM may disallow costs that are unreasonable or inadequately recorded. The Contractor is notified of any disallowed amounts.

Common Pitfalls

Poor record-keeping is the primary cause of disallowed costs. The Contractor must maintain contemporaneous, auditable records of all resources used.

Related Clauses