nec4engine
HomeClausesClause 54.4
Back to clause search
Section 5Payment

Clause 54.4

Final Assessment of Contractor's Share (Option C)

Purpose

Under Option C, the Project Manager makes a final assessment of the Contractor's share using the final Price for Work Done to Date and the final total of the Prices. This share is included in the final amount due.

Practical Application

The final share is calculated after all Defined Cost has been finalised and all CEs implemented. The assessment compares the actual final PWDD against the final total of the Prices.

Common Pitfalls

The final share can differ significantly from the preliminary assessment if late CEs or cost adjustments are made. The Contractor should track the expected final share throughout the project.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.