Notification by PM
The PM notifies the Contractor of a CE within one week of becoming aware of it.
The PM has an active duty to notify CEs. The PM cannot simply rely on the Contractor to identify all events.
If the PM fails to notify within one week, the Contractor may still notify under 61.3.