Section 6Compensation Events

Clause 62.3

PM's Response to Quotation

Purpose

The PM responds within two weeks, either accepting or giving reasons for not accepting. Silence = acceptance.

Practical Application

If the PM does not respond within two weeks, the quotation is treated as accepted.

Common Pitfalls

The PM must give reasons for non-acceptance. Reasons such as 'not agreed' without explanation are insufficient.