Clause 62.1

Quotation for CE

Purpose

The Contractor submits a quotation for a CE within three weeks, including time and cost impact.

Practical Application

Quotations must address both time and cost. A quotation for time only or cost only is incomplete.

Common Pitfalls

The three-week period can be extended by agreement. Request extension before the deadline, not after.