Sectional Completion
The Works Information defines sections of the works with separate Completion Dates.
Each section has its own Completion Date and may have its own delay damages. CEs affecting a section are assessed separately.
If sections are interdependent, a CE affecting one section may delay others. Assess cumulative impacts carefully.