Section 2The Contractor's Main Responsibilities

Clause 20.3

Design — Contractor Design

Purpose

The Contractor submits the design of the parts it is required to design to the PM for acceptance. The PM accepts the design if it complies with the Works Information.

Practical Application

Submit design deliverables in stages as agreed in the Works Information. The PM reviews each submission against the scope and specifications.

Common Pitfalls

PM acceptance of the design does not reduce the Contractor's design liability. Fitness for purpose remains the standard unless the Works Information states otherwise.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.