Clause 31.3

Revised Programme

Purpose

The Contractor submits a revised programme when instructed, or when a CE delays Completion.

Practical Application

Each CE should trigger a programme revision. This shows the assessed delay and supports the CE quotation.

Common Pitfalls

Not revising the programme after a CE makes it harder to substantiate delay claims later.