Section 3Time

Clause 35.4

Completion — Deferment

Purpose

The Employer may defer the starting date or access to parts of the Site. The period of deferment is stated in the Contract Data.

Practical Application

Deferment allows the Employer to delay the project start for funding, approvals, or other reasons. The maximum deferment period is typically stated in the Contract Data.

Common Pitfalls

Deferment beyond the stated period is a CE. The Contractor is entitled to additional time and cost for extended deferment.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.