Section 4Testing and Defects

Clause 41.6

Cost of Repeat Tests

Purpose

The Project Manager assesses the cost incurred by the Client in repeating a test or inspection after a Defect is found. The Contractor pays the amount assessed. The Contractor's own cost of carrying out the repeat test is not included.

Practical Application

The Client's cost of repeat testing (e.g., Supervisor's time, additional materials, facility hire) is assessed by the PM and paid by the Contractor. The Contractor bears its own repeat testing costs separately.

Common Pitfalls

The assessment covers only the Client's direct costs of the repeat test. If the repeat test causes programme delay, the delay may be a compensation event or may affect delay damages.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.