Clause 43.3

Defects — Late Correction

Purpose

If the Contractor corrects a defect after the defect correction period has ended but before the Employer corrects it, the Employer may still recover the costs of arranging the correction.

Practical Application

Late correction by the Contractor does not automatically avoid cost recovery by the Employer. The Employer's reasonable costs of administration and supervision of the correction are recoverable.

Common Pitfalls

If the Employer has already contracted with a third party to correct the defect, the Contractor's late correction may not cancel the Employer's contractual obligations to that third party.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.