Uncorrected Defects
If the Employer decides not to have an uncorrected defect corrected, the defect is accepted and the Prices are reduced. The reduction is assessed by the PM if not agreed.
The Employer may choose to accept financial compensation instead of physical correction if the defect is minor or the correction cost is disproportionate.
Accepting a defect does not waive the Employer's rights regarding latent defects that later manifest. The acceptance relates only to the notified non-conformance.