Acceptance of Defects
The Employer may accept a defect. If the Employer accepts a defect, the Prices are reduced by an amount agreed by the Contractor and PM.
Accepting a defect is a commercial decision. The deduction reflects the reduced value of the work due to the defect.
If the amount of reduction cannot be agreed, the PM assesses it. The Contractor may challenge the PM's assessment through adjudication.