Section 5Payment

Clause 55.4

Acceptance of Activity Schedule Revision

Purpose

Under Option A, a reason for not accepting a revision of the Activity Schedule is that it does not relate to the operations on the Accepted Programme, the changed Prices are not reasonably distributed between incomplete activities, or the total of the Prices is changed.

Practical Application

The PM can reject a revised Activity Schedule if the activity breakdown no longer reflects the programme, or if prices are allocated unfairly. The total Prices must remain unchanged.

Common Pitfalls

If the PM rejects a revision, the old Activity Schedule remains in effect, which may no longer reflect the Contractor's planned work. This complicates CE assessments using out-of-date activity values.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.