CE — Instruction Changing the Works Information
The PM gives an instruction to change the Works Information. This is the most common CE type.
Any PM instruction that changes scope, specification, sequence, or constraints is a CE.
Verbal instructions on site may constitute a change. Confirm all verbal instructions in writing promptly.