CE — Unnecessary Delay Caused by a Test or Inspection
A test or inspection done by the Supervisor causes unnecessary delay.
Delays caused by tests or inspections carried out by the Supervisor are compensation events.
The delay must be unnecessary — normal testing delays are not covered.