CE — Correction of Defects by Employer

Purpose

The Employer corrects a defect that was not the Contractor's responsibility, or instructs the Contractor to correct a defect caused by an Employer risk.

Practical Application

If the Supervisor incorrectly notifies a defect that later proves to be an Employer risk, the correction work is a CE. The Contractor is entitled to time and cost for the instructed correction.

Common Pitfalls

Distinguish between the Contractor's obligation to correct its own defects (own cost) and correction of defects caused by Employer risks (CE). The cause of the defect determines entitlement.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.