CE — Weather Measurement
A weather measurement is recorded within a calendar month, before the Completion Date for the whole of the works, and at the place stated in the Contract Data, the value of which, by comparison with the weather data, is shown to occur on average less frequently than once in ten years. Only the difference between the weather measurement and the weather which the weather data show to occur on average less frequently than once in ten years is taken into account.
Weather is assessed monthly, at the place stated in the Contract Data, against the once-in-ten-years benchmark.
Weather measurements after the Completion Date for the whole of the works are not compensation events.