CE — Client Does Not Provide Something
The Client does not provide something which it is to provide by the date shown on the Accepted Programme.
Anything the Client is to provide — information, materials, facilities — must be provided by the date on the Accepted Programme.
The trigger date is the date on the Accepted Programme, not the Contract Data.