Section 6Compensation Events

Clause 61.8

No Notification After the Defects Certificate

Purpose

A compensation event is not notified by the Project Manager or the Contractor after the issue of the Defects Certificate.

Practical Application

No compensation events may be notified once the Defects Certificate has been issued.

Common Pitfalls

Events arising after the Defects Certificate are outside the compensation event regime.

Related Clauses