Clause 62.2

Quotation Content

Purpose

The quotation includes proposed changes to Prices, Completion Date, and Key Dates.

Practical Application

Quantify both the time delay and associated cost. Reference the Accepted Programme for delay assessment.

Common Pitfalls

Do not forget to include fee and overhead. Ensure the quotation covers all direct and indirect costs.