Clause 62.5

Instructions Following Quotation

Purpose

If the PM does not accept the quotation, the Contractor may be instructed to submit an alternative quotation.

Practical Application

The PM may request a revised quotation if the original is not acceptable. The PM gives reasons and guidance.

Common Pitfalls

Multiple rounds of quotation can be time-consuming. Ensure the first quotation is well-prepared to avoid iterations.

Related Clauses

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.