Section 7Title

Clause 70.1

Title to Plant and Materials

Purpose

Title to Plant and Materials passes to the Employer when the Contractor is paid for them or when they are brought on to the Site, whichever is earlier.

Practical Application

Title transfer protects the Employer's interest in materials stored on Site or in transit. The Contractor clearly identifies Employer-owned items.

Common Pitfalls

If materials are stored off-Site, title may not pass until payment. The Contractor should have a separate vesting agreement for off-Site materials if required.

Related Clauses