Objects and Materials — Fossils and Antiquities
If the Contractor finds objects of value or interest (e.g., fossils, coins, antiquities, or structures) on the Site, the Contractor notifies the PM. The PM instructs how to deal with them.
Found objects are the Employer's property. The Contractor stops work in the affected area and follows the PM's instructions. The instruction is a CE.
The Contractor must not remove or disturb found objects without PM instruction. Unauthorised removal may breach the contract and applicable law.