Objects and Materials — Fossils and Antiquities

Purpose

If the Contractor finds objects of value or interest (e.g., fossils, coins, antiquities, or structures) on the Site, the Contractor notifies the PM. The PM instructs how to deal with them.

Practical Application

Found objects are the Employer's property. The Contractor stops work in the affected area and follows the PM's instructions. The instruction is a CE.

Common Pitfalls

The Contractor must not remove or disturb found objects without PM instruction. Unauthorised removal may breach the contract and applicable law.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.