Section 9Disputes and Termination

Clause 93.6

Contractor's Share on Termination (Options C, D)

Purpose

The Project Manager's assessment of the Contractor's share is added to the amounts due to the Contractor on termination if there has been a saving, or deducted if there has been an excess.

Practical Application

Under target cost Options C and D, the Contractor's share mechanism applies even on termination. Any saving or excess up to the termination date is included in the termination payment.

Common Pitfalls

The share calculation on termination may be based on incomplete cost data. The Contractor should ensure all costs up to the termination date are fully recorded and submitted.

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.