nec4engine
HomeClausesClause 30.3
Back to clause search
Section 3Time

Clause 30.3

Meeting Key Dates

Purpose

The Contractor does the work so that the Condition stated for each Key Date is met by the Key Date. Key Dates require specific conditions to be achieved by stated dates, distinct from overall Completion.

Practical Application

Key Dates are defined in the Contract Data with associated conditions. The Contractor plans and executes work to meet each condition by its Key Date, even if overall Completion is later.

Common Pitfalls

Failing to meet a Key Date condition may trigger the Client's right to recover additional costs under clause 25.3. Key Date failures are distinct from late Completion and have separate financial consequences.

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.