Clause 35.2

Completion — Sectional Completion

Purpose

If the Works Information identifies sections of the works, each section has its own Completion Date. The Contractor achieves Completion of each section by its sectional Completion Date.

Practical Application

Sectional Completion allows phased handover and separate delay damages for each section. Each section's Completion is certified independently by the Supervisor.

Common Pitfalls

Interdependence between sections can cause cascading delays. A CE affecting one section may delay others even if that section's works are unaffected.

Related Clauses

📖 This summary is for reference. For the full, authoritative NEC4 contract text — including all amendments, guidance notes, and flow charts — visit the official NEC website.

Purchase Official NEC4 →

⚠️ This commentary is for reference only. Always refer to the full NEC4 contract text and seek professional legal or contractual advice for your specific project.