CE — Correction to an Assumption
The Project Manager notifies the Contractor of a correction to an assumption which the Project Manager stated about a compensation event.
Where the PM stated assumptions for assessing a compensation event and later corrects them, the correction is itself a compensation event.
Keep track of assumptions stated in instructions to submit quotations.